Tender logistics · Tender submission

Tender-stage logistics methodology and phased site planning

CLC developed the written logistics methodology and coordinated drawings for a tender covering two work areas on an operational estate. The tender team needed to know how deliveries, welfare, material handling and working space would change as the buildings went up.

Discuss a tender logistics brief

Turning the programme into logistics proposals

We coordinated the methodology and layouts with the tender construction and design-release programmes. A route drawing showed how vehicles would approach and leave the estate. An overall logistics plan related both work areas to the shared access arrangements. The establishment drawings then showed where each team could start work, including a main welfare setup for the project and ancillary provision at the second work area.

How handling and laydown changed between phases

One area had little room between the structure and its working boundary. The phased layouts moved handling positions and short-term laydown as erection progressed. At the other, temporary working space had to be released for later permanent works. The methodology set out how to book loads against an installation sequence, check that the receiving area was clear and avoid building up stock that crews would have to move again.

What the tender team could review

The written method and drawings gave the team a common basis for reviewing the tender programme, access, segregated pedestrian movement, welfare, storage and the relationship with continuing estate operations. The dimensional sheets supported those decisions by showing the available widths and local pinch points.

The tender methodology and eleven drawings

The submission comprised the written tender construction logistics methodology and eleven drawings. The set comprised one route plan, one overall access and logistics plan, seven work-area establishment and phase plans, and two drawings recording available space.

Drawing groupSheetsPurpose
Access and egress route plan1Approach and departure of construction vehicles
Overall access and logistics plan1How the two work areas share estate access
First work area4Establishment and three phased arrangements
Second work area3Establishment and two phased arrangements
Dimensions and available space2One supporting drawing per work area

Issue status and limitations

The package was issued for tender. Access concepts and temporary working space still required confirmation. Final plant selection, lifting arrangements and temporary works design remained with the appointed specialists.

Discuss a tender logistics brief

Send the tender programme, site layouts, access constraints and tender return date. We’ll confirm the scope, fee and delivery date after reviewing the brief.

Request a project quotation