Site Logistics Plans
Site logistics plans for London and UK construction projects. CLC prepares coordinated drawings showing how access, deliveries, storage, welfare and day-to-day activities fit within the available site space, supporting planning, tender and pre-construction teams.
Need the written strategy for planning or condition discharge? See our Construction Logistics Plan (CLP) service.
Request a site logistics plan quotePlan the site as a whole
We coordinate hoarding and gates, loading areas, storage and waste zones, plant locations, welfare interfaces and internal movement routes. Public footways, cyclists and neighbouring access are considered alongside site operations.
What should a site logistics drawing show?
The drawing should make the proposed site arrangement clear enough for the project team to review how it will operate. Depending on the agreed scope, it can identify:
- Site boundaries, hoarding, vehicle gates and separate pedestrian entrances.
- Vehicle access and egress, delivery and unloading positions, and turning or reversing areas.
- Material storage, waste collection and routes between unloading points and the work areas.
- Proposed crane and hoist locations, with access and loading interfaces coordinated against the specialist information supplied.
- Welfare and compound areas, pedestrian routes and separation from vehicle movements.
- Marshal positions and delivery-control notes, including whether any holding space is actually available.
- Changes to access, loading or storage between construction stages.
The layout needs to show how these arrangements fit together. For example, a storage area should not obstruct the delivery route, and a welfare entrance needs a usable pedestrian connection. Unconfirmed dimensions and specialist design interfaces are identified for further coordination.
Your deliverables
CAD-based logistics drawings issued in PDF, showing the proposed setup, movement routes and logistics zones. Notes explain site constraints and project requirements. Design-development updates are included to the extent agreed in the scope.
Logistics beside live roads
For replacement works beside live roads, CLC coordinated a planning-stage CLP, vehicle routing and separate layouts for two work areas.
| Project item | What CLC assessed |
|---|---|
| Working space | Located delivery and removal activities around the available space, retained trees and adjoining public routes. |
| Vehicle arrivals | Related the construction vehicle route to a call-forward procedure so loads could be held at origin until space was available. |
| Public interfaces | Distinguished operative access from walking and cycling routes and identified where highway agreements or specialist design were still needed. |
Coordinate the interfaces
Where required, the layout can be developed alongside Swept Path Analysis, Vehicle Access and Routing Plans, Traffic Management Plans, Construction Phasing Plans and Welfare & Compound Planning. This helps the team review the same access and loading strategy across the drawing package. For a coordinated set of layouts, see our pre-construction logistics coordination service.
Information and fees
Send the site location, available scaled drawings, proposed access, construction activities and programme. Include the tender brief or planning condition, the stages to be shown and your required issue date. Fees reflect the agreed project scope. A fixed fee follows review of the brief.
Site logistics plan FAQs
What is a site logistics plan?
A site logistics plan is a drawing showing how construction activities share the available space: vehicle and pedestrian access, loading, storage, waste, welfare and plant locations. It helps the project team coordinate a workable arrangement for the proposed construction stage.
Is it the same as a Construction Logistics Plan?
A site logistics drawing illustrates the physical arrangements. Our written Construction Logistics Plans explain the wider delivery strategy, routing, programme and management measures required by the project brief or planning condition. A drawing can support a CLP, but does not automatically replace the required written report. If the drawing responds to a planning condition, our CLP condition-discharge support explains how the report and drawing scope are agreed.
What information should I send?
Send the latest site or architectural drawings, site address, proposed works, access constraints and programme. Include any planning condition or tender brief. Where details are not confirmed, we identify assumptions and the information needed to develop the layout.
Can you show different construction phases?
Where agreed in the scope, separate layouts can show how access, loading, welfare and storage change through enabling works, demolition and main construction. The number of phases and drawings is confirmed with the fee.
Will I receive a PDF drawing?
Yes. CAD-based drawings are issued as annotated PDFs for review and coordination. Drawing scales, sheet sizes and any additional file formats are agreed for the project.
Do you work on constrained London sites?
CLC supports London and UK projects. On constrained London sites, layouts consider limited storage, neighbouring access, public footways, cyclists and the interface with the highway. Proposed highway arrangements remain subject to the relevant approvals; the drawing itself does not grant permission to occupy or control the highway.
Request a site logistics quotation
Send the site boundary, available layout drawings and the works you need to show. We’ll confirm the drawing scope, fixed fee and delivery timeframe.
Request a site logistics plan quoteProject example: a constrained London site
For specialist replacement works beside strategic highways, CLC prepared a planning-stage CLP with coordinated access, routing and site logistics information. Restricted turning space, tree-protection areas and a lack of local vehicle waiting space shaped the proposed delivery strategy.
The work identified arrangements requiring further contractor and specialist development, including final vehicle selection, swept path verification, lifting plans and highway approvals.