Revising a CLP and its supporting drawings for an occupied site

CLC revised a contractor’s existing Construction Logistics Plan in response to highways comments. The submission needed to show how deliveries would be booked, how vehicles would reach and leave the work area, and how the contractor would monitor those arrangements while the site remained occupied.

Discuss a CLP condition response

Coordinating the submission

We retained the contractor’s programme as an input. Across six phases, we related the anticipated loads to a vehicle forecast and movement schedule, distinguishing a vehicle visit from the two highway movements it generates. We coordinated that information with the site-establishment plan, unloading space and the route to the site.

Connecting the maps and the vehicle assessment

Six mapping sheets set the works in their regional and local context and identified the site boundary, construction routing, nearby receptors, and walking and cycling interfaces. A principal access and egress route plan and a site logistics plan supported the written controls. Three tracking sheets tested rigid-vehicle access, internal manoeuvring and departure, with a separate close-up of the entrance movement.

Making the controls usable

The revised CLP included driver briefing information and set out how the contractor would compare actual arrivals and departures with bookings and forecast peaks, respond to complaints and update the plan when assumptions changed. The contractor was responsible for operating those controls.

What CLC delivered

An issued revision to the contractor’s CLP with eight appendices. These bring together the contractor’s programme, six maps, a forecast, movement schedule, principal route plan, site logistics drawing, three tracking sheets and a driver information sheet.

Submission componentHow it was used
ProgrammeContractor’s programme carried into the revised CLP as an input.
Maps and routingSix context, access and interface maps plus a principal route plan.
DemandA phase-based vehicle forecast and supporting movement schedule.
Site setup and trackingSite logistics plan and three vehicle sheets covering entry, departure and an entrance detail.
Driver briefingDriver information sheet for controlled issue with the confirmed booking.

Issue status and limitations

CLC issued the coordinated report for planning submission. The three tracking sheets retained their preliminary assessment status within that issue. Their findings depended on the vehicle, physical clearances and space available before use.